The generator is on order, the pad is on the concrete schedule, and the electrician has reserved a crew. Then the gas utility asks for the engine's full-load fuel demand, and nobody has it. The electrical selection came from the panel nameplate, while the...
A lot of generator decisions get made too late. The building is nearly ready. The electrical gear is in. Controls are being checked. Inspectors are coming. Then someone asks a simple question that should have been settled months earlier: is live gas available at the...